1 - Achieving and installing /waste water treatment unit (1750 m3 / h) : - the achievement percentage is 60%.
2 – Installing of 9 tanks of variant sizes in the Basra refinery : - Constructing of 2 tanks (10,000 b / d) finished and the third is being.
3 – Installing three steam boilers, (150 tons / day ) in the Basra refinery .
4 - Constructing a kindergarten and nursery building in the residential unit : - the achievement percentage is 65%.
5 - Constructing 38 residential houses in Basra refinery : - the Company is now Constructing 38 houses in the residential unit of the company the achievement percentage is 90 %.
6 - Constructing of the raw water pipeline from the Garmat Ali
7 - Constructing of department building in Basra refinery counters : - Work is continuing at a completion rate of 12%
8 - Constructing counters in department building refinery in Dhi Qar : - a work in progress and a completion rate of 98%
9 – A contract of to designing with the oil city residential: - A contract was signed with the National Center for engineering studies for the purpose of preparation of engineering.
10 - Constructing warehouses in the Basra refinery:Work is continuing at a completion rate of 5%
11 - Constructing 20 residential houses in Dhi Qar refinery : - Work is continuing at a completion rate of 4%
12 - Constructing supplement to the House intermission in Dhi Qar refinery : - Work is continuing at a completion rate of 40%
13 - Created regimental headquarters in Dhi Qar refinery : - Work is continuing now.
14 - Created a security fence in Dhi Qar refinery : - Work is continuing and completion of 25%
15 - Achieving and installing water purification unit in the Garmat ali .
16 - Achieving the connecting of the pipeline network for the new units: - Work is continuing at a completion rate of 70%