1 - Achieving and installing  /waste water treatment unit (1750 m3 / h) : - the achievement percentage is 60%.

2 – Installing of 9 tanks of variant sizes in the Basra refinery : - Constructing of  2 tanks (10,000 b / d)  finished and the third is being.


3 – Installing three steam boilers, (150 tons / day ) in the Basra refinery .


4 - Constructing a kindergarten and nursery building in the residential unit : - the achievement percentage is 65%.


5 - Constructing 38 residential houses in Basra refinery : - the Company is now  Constructing 38 houses in the  residential unit of the company the achievement percentage is  90 %.


6 - Constructing of the raw water pipeline from the Garmat Ali                                             

7 - Constructing of department building in Basra refinery counters : - Work is continuing at a completion rate of 12%

8 - Constructing counters in department building refinery in Dhi Qar : - a work in progress and a completion rate of 98%


9 – A contract of  to designing  with the oil city residential: - A contract was signed with the National Center for engineering studies for the purpose of preparation of engineering.


10 - Constructing  warehouses in the Basra refinery:Work is continuing at a completion rate of 5%


11 - Constructing 20 residential houses in Dhi Qar refinery : - Work is continuing at a completion rate of 4%


12 - Constructing supplement to the House intermission in Dhi Qar refinery : - Work is continuing at a completion rate of 40%


13 - Created regimental headquarters in Dhi Qar refinery : - Work is continuing now.


14 - Created a security fence in Dhi Qar refinery : - Work is continuing and completion of 25%


15 - Achieving and installing  water purification unit in the Garmat ali .


16 - Achieving  the connecting of the pipeline network for the new units: - Work is continuing at a completion rate of 70%